πŸ“’ New Earnings In! πŸ”

MNTK (2025 - Q2)

Release Date: Aug 07, 2025

...

Stock Data provided by Financial Modeling Prep

Current Financial Performance

MNTK Q2 2025 Financial Highlights

$45.1 million
Total Revenue
+4.1%
$5.0 million
Adjusted EBITDA
-28.6%
$5.5 million
Net Loss
$2.4 million
Operating Loss

Key Financial Metrics

RNG Production

1.4 million MMBtu

Flat YoY

RNG Revenue

$40.8 million
5.1%

Renewable Electricity Revenue

$4.3 million
4.5%

RNG Operating Expenses

$17.0 million
22%

Renewable Electricity O&M Expenses

$4.8 million
2%

Cash from Operations (6M)

$17.3 million
19.3%

Capital Expenditures (6M)

$45.3 million

Period Comparison Analysis

Total Revenue

$45.1 million
Current
Previous:$43.3 million
4.2% YoY

Adjusted EBITDA

$5.0 million
Current
Previous:$7.0 million
28.6% YoY

Net Income/Loss

-$5.5 million
Current
Previous:-$0.7 million
685.7% YoY

Operating Income/Loss

-$2.4 million
Current
Previous:$0.9 million
166.7% YoY

RNG Revenue

$40.8 million
Current
Previous:$38.8 million
5.2% YoY

Renewable Electricity Revenue

$4.3 million
Current
Previous:$4.5 million
4.4% YoY

RNG Operating Expenses

$17.0 million
Current
Previous:$13.9 million
22.3% YoY

Renewable Electricity O&M Expenses

$4.8 million
Current
Previous:$4.7 million
2.1% YoY

Earnings Performance & Analysis

Average RIN Price Q2 2025

$2.42

Down 22.4% YoY

RINs Self-Marketed Q2 2025

11.1 million
10.5%

EBITDA

$4.6 million
31.3%

Discrete Expenses Q2 2025

$4.7 million

Nonrecurring maintenance & stock comp

Financial Guidance & Outlook

2025 RNG Production Guidance

5.8-6.0 million MMBtu

Unchanged from prior guidance

2025 RNG Revenue Guidance

$150M-$170M

Unchanged from prior guidance

2025 Renewable Electricity Guidance

178,000-186,000 MWh

Unchanged from prior guidance

2025 Renewable Electricity Revenue

$17M-$18M

Unchanged from prior guidance

Surprises

Increase in Total Revenues Despite Lower RIN Prices

$45.1 million in Q2 2025 revenues, up 4.1% from $43.3 million in Q2 2024

Total revenues in the second quarter of 2025 were $45.1 million, an increase of $1.8 million or 4.1% compared to $43.3 million in the second quarter of 2024, primarily related to timing of revenues recognized under a short-term fixed price contract.

Significant Decrease in Average Realized RIN Prices

$2.42 in Q2 2025 vs. $3.12 in Q2 2024, a 22.4% decrease

Average pricing realized on RIN sales during the second quarter of 2025 was $2.42 as compared to $3.12 during the second quarter of 2024, a decrease of approximately 22.4%.

Increase in Operating and Maintenance Expenses

$17.0 million in Q2 2025, up 22% from $13.9 million in Q2 2024

Our operating and maintenance expenses for our RNG facilities during the second quarter of 2025 were $17.0 million, an increase of $3.1 million or 22% compared to $13.9 million during the second quarter of 2024.

Widening Net Loss

$5.5 million net loss in Q2 2025 vs. $0.7 million net loss in Q2 2024

Net loss of the second quarter of 2025 was $5.5 million, an increased loss of $4.8 million as compared to $0.7 million for the second quarter of 2024.

Impact Quotes

The joint venture aims to address limited RNG transportation capacity by creating unique pathways to increase RIN separation and market access.

We do not expect the approximate $1.8 million within RNG and the $1.4 million within our REG segments to recur in the second half of the year as these were planned expected preventative maintenance items.

The favorable change in swine renewable energy credit generation legislation has compelled us to refine development efforts in North Carolina to focus on feedstock exclusively from swine waste and electricity generation.

Based on our Pico project study, we are better positioned to understand the Inflation Reduction Act investment tax credits for qualifying projects and assets.

We continue to manage through regulatory uncertainty but reaffirm our full year 2025 outlook with no changes to RNG production and revenue guidance.

The EPA is still evaluating the imbalance between D3 RIN production and the proposed RVO, which may lead to adjustments in future volume requirements.

Notable Topics Discussed

  • The EPA released partial waivers for 2024 and proposed reductions for 2025, 2026, and 2027, affecting cellulosic biofuel volume requirements.
  • Montauk sold all its 2024 RINs, with limited direct impact from the final 2024 waiver, but future volumes are expected to be constrained by EPA's capacity estimates.
  • EPA's proposal suggests that growth in RNG utilization for transportation will be limited by capacity constraints of CNG, LNG, and biogas, influencing future RIN market dynamics.
  • Montauk's joint venture with Pioneer Renewables, GreenWave Energy Partners, aims to address capacity limitations by creating proprietary transportation pathways for RNG, potentially offsetting regulatory constraints.
  • The company is monitoring EPA's evaluation of RVOs, which are still within a consultation period, and expects potential adjustments based on industry RIN generation rates.
  • Montauk is developing a project in North Carolina focused on converting swine waste into electricity, with initial phase expected to commence production in early 2026.
  • Recent legislation in North Carolina favorably changed renewable energy credits (RECs) for swine waste projects, prompting a focus on feedstock from swine waste exclusively for electricity generation.
  • The project scope has been refined to optimize feedstock collection, pelletization, and transportation, with capital investment estimates increased to $180-$220 million for the first phase.
  • The company has executed a power purchase agreement (PPA) for 10 years, with an average price of $48 per megawatt-hour, aligned with regional power markets.
  • Montauk is engaging with utilities and local authorities to leverage new legislation, aiming to expand the project and potentially scale up based on initial success.
  • Montauk completed construction and commissioning of a second RNG processing facility at Apex landfill, adding 2,100 MMBtu per day of capacity.
  • The second facility was driven by increased waste intake projections from the landfill host, indicating ongoing excess capacity as waste intake grows.
  • The company is planning to capture, clean, and liquefy 140,000 tons of CO2 annually, with a 15-year contract starting in late 2027, representing a significant new revenue stream.
  • The CO2 project involves transporting captured CO2 to a Texas-based e-methanol facility, with initial engineering and design work underway and capital expenditures for long-lead items incurred in Q2 2025.
  • Montauk's strategy includes expanding biogas utilization and integrating new processing facilities to support future growth and revenue diversification.
  • Montauk announced a collaboration with Emvolon to convert biogas into green methanol, with a pilot project at Houston's Atascocita facility exceeding expectations.
  • The partnership aims to produce up to 50,000 metric tons of green methanol annually by 2030, with no immediate short-term financial benefits but strategic long-term potential.
  • The company is also advancing its carbon capture initiatives, including engineering design and equipment evaluation for CO2 liquefaction and sequestration, with commissioning targeted for 2027.
  • Montauk sees these projects as balancing revenue streams, with green methanol and carbon capture offering high-value, tax-credit-eligible products that complement RNG operations.
  • The collaboration leverages patented technology and industry relationships to develop proprietary pathways for emissions reduction and renewable fuel production.
  • Total revenues for Q2 2025 were $45.1 million, up 4.1% from Q2 2024, driven by timing of RIN sales and higher commodity prices.
  • Adjusted EBITDA declined 28.6% to $5.0 million, impacted by discrete expenses and lower RIN prices, with a net loss of $5.5 million compared to a $0.7 million loss in Q2 2024.
  • RIN inventory and timing of RIN separation affected revenue recognition, with approximately 3 million RINs generated but unseparated as of June 30, 2025.
  • Operating expenses increased due to scheduled preventative maintenance, but management expects these to be non-recurring in the second half of 2025.
  • The company maintains full-year 2025 guidance, projecting RNG production of 5.8-6 million MMBtu and revenues of $150-$170 million, despite regulatory uncertainties.
  • Montauk is preparing for the effects of the July 4, 2025, enactment of the 'One Big Beautiful Bill Act,' which modifies tax credits and incentives.
  • The company expects to recognize $1-2 million in investment tax credits for the Apex RNG project, with potential for up to 75% of project capital to qualify.
  • Changes in tax law, including extensions and enhancements of the Tax Cuts and Jobs Act and Inflation Reduction Act, are expected to influence future tax benefits and project economics.
  • Montauk is evaluating the impact of these legislative changes on ongoing and future projects, including Pico digestion expansion and other qualifying assets.
  • The company anticipates that new tax credits and incentives will support project financing and profitability in the coming years.
  • Q2 2025 saw a 22% increase in RNG facility operating and maintenance expenses, primarily due to scheduled preventative maintenance and wellfield enhancements.
  • The company expects similar non-recurring maintenance costs in the second half of 2025, with some expenses related to equipment upgrades at Apex, McCarty, Rumpke, and Atascocita.
  • Electricity generation decreased slightly by 6.7%, partly due to planned engine maintenance at Bowerman, impacting revenue and output.
  • Montauk is optimizing maintenance schedules to minimize disruptions and expects these costs to align with historical run rates moving forward.
  • Impairments of $0.4 million were recorded, mainly for assets deemed obsolete or nonoperable, but no impairments related to future cash flow projections were reported.
  • The North Carolina project shifted focus to exclusively use swine waste for electricity generation, removing agricultural components to streamline operations.
  • Montauk is increasing capital investment estimates for the North Carolina project to $180-$220 million, emphasizing feedstock collection, pelletization, and transportation improvements.
  • The company is exploring additional expansion opportunities, including rail transportation and further processing, to enhance project scalability and efficiency.
  • Management highlighted the importance of legislative changes in enabling project refinement and expansion, with a focus on cost reduction and operational flexibility.
  • The project aims to leverage patented reactor technology and local incentives to maximize long-term profitability and environmental benefits.
  • Montauk's second RNG processing facility at Apex enhances capacity, supporting increased waste intake and biogas production.
  • The company is developing infrastructure for capturing, liquefying, and transporting CO2, with a 15-year contract to deliver 140,000 tons annually starting in late 2027.
  • Initial engineering and design work for CO2 processing equipment is underway, with capital expenditures for long-lead items incurred in Q2 2025.
  • The strategic focus on biogas and CO2 infrastructure aims to diversify revenue streams and capitalize on tax credits under the Inflation Reduction Act.
  • Montauk's integrated approach combines RNG, green methanol, and carbon sequestration to position itself as a leader in renewable fuels and emissions reduction.
  • Montauk reaffirmed its full-year 2025 outlook despite regulatory uncertainties, maintaining RNG production guidance of 5.8-6 million MMBtu.
  • The company is actively managing through regulatory and legislative changes, including EPA RVO proposals and tax law updates, to optimize project economics.
  • Management emphasized the strategic importance of proprietary pathways and joint ventures to offset potential growth constraints imposed by regulatory agencies.
  • The company remains optimistic about long-term growth in RNG and renewable fuels, leveraging legislative changes and technological innovation.

Key Insights:

  • Montauk reaffirms full-year 2025 guidance with RNG production expected between 5.8 and 6 million MMBtu and revenues between $150 million and $170 million.
  • No short-term financial benefits are expected from the Emvolon joint development venture for green methanol production.
  • Renewable Electricity production is expected between 178,000 and 186,000 megawatt hours with revenues between $17 million and $18 million, unchanged from prior guidance.
  • Tax law changes from the One Big Beautiful Bill Act will be adopted starting Q3 2025, potentially impacting tax credits and provisions.
  • The company continues to manage regulatory uncertainty, particularly related to EPA RIN volume requirements and pricing.
  • Advancing development in North Carolina focused on swine waste feedstock for electricity generation, with a 10-year power purchase agreement at an average $48/MWh.
  • Collaborating with Emvolon on green methanol production from biogas, targeting up to 50,000 metric tons annual capacity by 2030.
  • Completed construction and commissioning of a second RNG processing facility at the Apex landfill, adding 2,100 MMBtu/day capacity.
  • Formed a joint venture, GreenWave Energy Partners, with Pioneer Renewables to provide proprietary transportation pathways for RNG and RIN separation.
  • Ongoing optimization of feedstock collection and transportation, including pelletization and upstream processing technologies.
  • Signed a 15-year contract for delivery of 140,000 tons/year of biogenic CO2 to a Texas e-methanol facility, with expected revenues of $170-$201 million over the term.
  • Management emphasized the strategic focus on North Carolina swine waste project leveraging favorable legislation and long-term fixed price contracts.
  • Management expects discrete maintenance expenses incurred in Q2 to not recur in the second half of 2025.
  • Management highlighted the impact of EPA regulatory changes on RIN pricing and volume requirements, noting limited direct impact from 2024 waivers but ongoing uncertainty for 2025 and beyond.
  • Tax benefits from investment tax credits related to recent projects are expected to positively impact 2025 tax provisions.
  • The company remains excited about growth opportunities in biogenic CO2 commodity production and green methanol development.
  • The joint venture aims to address limited RNG transportation capacity by creating unique pathways to increase RIN separation and market access.
  • EPA may reconsider RVO volumes due to current D3 RIN generation exceeding proposed targets for 2025-2027, but no definitive changes announced.
  • North Carolina swine project has significant expansion potential with multiple revenue streams including electricity, gas, and biochar products.
  • Operating and maintenance expenses are generally higher in the first half of the year due to planned outages, with expectations for lower expenses in the second half.
  • RNG operating expenses increased in Q2 due to planned preventative maintenance; these expenses are not expected to recur in the second half of 2025.
  • Royalty share increase in Q2 was a one-time impact related to Pico earn-out adjustments; expected to normalize around 20%.
  • The GreenWave joint venture involves capital contributions and technical expertise to create new RNG transportation and RIN separation pathways.
  • Accounts and other receivables totaled approximately $7.5 million with no expected collectibility issues.
  • As of June 30, 2025, Montauk had $50 million outstanding on its term loan and $20 million borrowed on its revolving credit facility, with $97.4 million available capacity.
  • Cash and cash equivalents net of restricted cash were approximately $29.1 million at quarter-end.
  • Discrete nonlinear expenses related to stock-based compensation and maintenance impacted Q2 results but are not expected to recur.
  • Impairments of $0.4 million were recorded in Q2 2025, related to obsolete or nonoperable assets.
  • The company is evaluating tax law changes from recent legislation and their impact on tax credits and provisions.
  • Management is actively budgeting for 2026 with expectations of stable operating expense run rates and continued project development.
  • Montauk's strategy includes expanding proprietary transportation pathways to mitigate regulatory constraints on RNG usage in transportation.
  • The 15-year CO2 delivery contract includes revenue sharing of tax attributes under the Inflation Reduction Act's Section 45Q.
  • The Emvolon collaboration represents a long-term strategic investment in carbon-negative fuel production with no near-term financial impact.
  • The EPA's biogas regulatory reform (BRRR) and cellulosic waiver credits have constrained D3 RIN pricing and availability in 2025.
  • The North Carolina project focuses exclusively on swine waste feedstock and electricity generation, optimizing feedstock processing to reduce costs.
Complete Transcript:
MNTK:2025 - Q2
Operator:
Good day, everyone, and thank you for participating in today's conference call. I would like to turn the call over to John Ciroli as he provides some important cautions regarding forward-looking statements and non-GAAP financial measures contained in the earnings material or made on this call. John, please go ahead. John Cir
John Ciroli:
Thank you, and good day, everyone. Welcome to Montauk Renewables earnings conference call to review the second quarter 2025 financial and operating results and developments. I'm John Ciroli, Chief Legal Officer and Secretary at Manta. Joining me today are Sean McClain, Montauk's President and Chief Executive Officer, to discuss business development; and Kevin Van Asdalan, Chief Financial Officer, to discuss our second quarter 2025 financial and operating results. At this time, I would like to direct your attention to our forward-looking disclosure statement. During this call, certain comments we make constitute forward-looking statements and as such, involve a number of assumptions, risks and uncertainties that could cause the company's actual results or performance to differ materially from those expressed in or implied by such forward-looking statements. These risk factors and uncertainties are detailed in Montauk Renewables' SEC filings. Our remarks today may also include non-GAAP financial measures. We present EBITDA and adjusted EBITDA metrics because we believe measures assist investors in analyzing our performance across reporting periods on a consistent basis by excluding items that we do not believe are indicative of our core operating performance. These non-GAAP financial measures are not prepared in accordance with generally accepted accounting principles. Additional details regarding these non-GAAP financial measures, including reconciliations to the most directly comparable GAAP financial measures can be found in our slide presentation and in our second quarter 2025 earnings press release and Form 10-Q issued and filed on August 6, 2025. These are available on our website at ir.montaukrenewables.com. [Operator Instructions] And with that, I will turn the call over to Sean.
Sean F. McClain:
Thank you, John. Good day, everyone, and thank you for joining our call. On June 13, 2025, the EPA released the partial waiver of the 2024 cellulosic biofuel volume requirement, the RFS standards for 2026 and 2027, the partial waiver of the 2025 cellulosic biofuel volume requirements and other changes in their proposed rule. The final 2024 cellulosic biofuel volume requirement was reduced from $1.090 billion to $1.010 billion D3 RINs. This reduction was based on actual volumes of D3 RINs generated in 2024. In addition, the EPA is making cellulosic waiver credits available for 2024 and as an additional compliance flexibility measure for obligated parties. This final rule has limited direct impact to Montauk as we have sold all of our 2024 RINs. For 2025, the EPA has proposed cellulosic biofuel volumes for 2025 to be reduced from $1.376 billion to $1.190 billion RINs and to make cellulosic waiver credits available for 2025. These proposals, coupled with the EPA's biogas regulatory reform rule of matching the production of RNG with the dispensing of RNG to transportation appear to have limited the pricing level at which the D3 RIN currently trades. The proposed cellulosic biofuel volume requirements for 2026 and 2027 are $1.300 billion and $1.360 billion D3 RINs, respectively. In justification of these lower- than-expected volumes and the suggestion that small refinery exemptions be potentially revisited, the EPA has expressed their view that cellulosic RIN generation from biogas, CNG, LNG during 2026 to 2030 will be constrained by the total usage capacity of CNG, LNG as transportation fuel. In the first quarter of 2025, we entered into an agreement with Pioneer Renewables Energy Marketing to form a joint venture, GreenWave Energy Partners. The primary goal of the joint venture is to help address this limited capacity of RNG utilization for transportation by offering third-party RNG volume producers access to exclusive, unique and proprietary transportation pathways. We expect to be the RIN separator for the joint venture and expect to receive separated RINs as our distributions. While we have yet to realize material benefits from the joint venture through the second quarter, we have begun successfully contracting, dispensing and separating RINs through these proprietary transportation pathways. We continue our development efforts in North Carolina with an expectation to commence production and revenue generation activities in early 2026. As previously noted, the favorable change in swine renewable energy credit generation legislation enacted by the state of North Carolina in 2024 has us engaged in various stages of negotiations with obligated utilities to provide RECs from our expected 2026 production. We have executed a power purchase agreement for the expected power to be produced from the first phase of electric production. The term of this PPA begins once we commission the facility and covers 100% of the electricity produced for 10 years. The PPA price is based on set tariffs and considers various impacts, including, but not limited to, demand, season and time of day, and we believe the average price considering these factors of $48 per megawatt hour is in line with various Southeastern United States power markets ranging from 40 to 60-megawatt hours. This favorable change in swine renewable energy credit generation legislation has compelled us to refine development efforts in North Carolina to focus on feedstock exclusively from swine waste, no longer inclusive of an agricultural component. Additionally, we've refined our production focus for this first phase to be exclusively electricity generation. Correspondingly, we continue to optimize the collection and transportation of swine feedstock from the collection farms to the centralized processing location, including the removal of low energy content liquid waste. Such efforts include the pelletization of collected waste and the incorporation of additional upstream processes using screw press and centrifuge technologies. Our feedstock collection and transportation optimization efforts are expected to have an impact on both the number of farm serviced as well as the associated equipment and operating costs. Given the opportunity set afforded by the change in legislation and our refined focus on both the feedstock optimization and increased electricity generation, we are increasing the range of capital investment expected for this first phase to $180 million to $220 million. The revised estimate of the total project to the extent impacting 2025 is included in our 2025 development capital expenditures range. We have successfully completed the construction and commissioning of a second RNG processing facility at the Apex landfill. As previously noted, the construction of the second facility was triggered by the landfill host projections of biogas feedstock volumes in excess of the original facilities production capacity, driven by the landfill host waste intake projections. The second facility provides us with an additional 2,100 MMBtu per day of production capacity. We continue to expect a period of excess production capacity as the landfill host continues to increase their waste intake. In 2024, we signed a contract for the annual delivery of 140,000 tons per year of biogenic carbon dioxide. We intend to capture, clean and liquefy CO2 at select Texas facilities, at which point, EE North America will transport it to a Texas-based e-methanol facility. The delivery term is expected to last 15 years with the first delivery expected to begin in late 2027. During the period prior to commissioning, we have been recognizing an exclusivity fee related to the minimum tons of CO2. The annual price per ton under the contract is adjusted by the U.S. Consumer Price Index. The agreement with EENA also includes a 50% sharing of any available tax attributes generated by us under Code Section 45Q, carbon dioxide sequestration credit in the inflation Reduction Act as applicable. There are other revenue sharing components under the agreement to the extent we're able to produce CO2 prior to EENA accepting delivery. Excluding any estimate of tax attributes and including a U.S. Consumer Price Index range of 2.5% to 3% annually, we estimate the total revenues under this 15-year term to provide an annual minimum of 140,000 tons of CO2 will range between $170 million to $201 million in total. We have completed the initial site surveys related to the location of the CO2 processing equipment, have evaluated equipment suppliers and started engineering design. We continue to target a commissioning start in 2027 and began incurring capital expenditures for long lead items and design engineering in the second quarter of 2025. Also in 2024, we announced a collaboration with Emvolon to transform methane emissions from waste stream biogas into high-value carbon-negative fuel. Leveraging Emvolon's patented technology, the initial pilot was a small-scale demonstration of recovering and converting biogas into green methanol. The initial pilot project at our Atascocita facility in Houston, Texas, exceeded its anticipated results. Following a successful field demonstration project together with Emvolon, we plan to deploy a portfolio of biogas sites with an aggregate annual production capacity of up to 50,000 metric tons of green methanol by 2030. We do not expect short-term financial benefits from this joint development venture nor a disruption to our operations. And with that, I will turn the call over to Kevin.
Kevin Andrew Van Asdalan:
Thank you, Sean. I will be discussing our second quarter 2025 financial and operating results. Please refer to our earnings press release and the supplemental slides that have been posted to our website for additional information. Our profitability is highly dependent on the market price of environmental attributes, including the market price of RINs. As we self- market a significant portion of our RINs, a strategic decision not to commit to transfer available RINs during a period will impact our revenue and operating profit. The impact of the EPA rule making associated with the implementation of BRRR K2 separation and the extension of the 2024 RIN compliance period has temporarily impacted our commitment timing of our 2025 RNG production. At June 30, 2025, we had approximately 3 million RINs generated and unseparated. We expect this timing between RINs generated but unseparated and RINs available for sale to only impact 2025, which is the year BRRR became effective. We had approximately 108,000 RINs in inventory from 2025 RNG production as of June 30, 2025. These RINs were transferred in July under a commitment entered into in June 2025 at a price of $2.42. The average D3 RIN index price for the second quarter of 2025 was approximately $2.36. Total revenues in the second quarter of 2025 were $45.1 million, an increase of $1.8 million or 4.1% compared to $43.3 million in the second quarter of 2024. The increase is primarily related to timing of revenues recognized under a short-term fixed price contract in the 2025 second quarter when compared to the amount of RINs available but unsold at June 30, 2024. Partially offsetting this impact was a decrease in realized RIN pricing during the second quarter of 2025 to $2.42 compared to $3.12 in the second quarter of 2024 and a reduction in RINs available for sale as a result of the EPA BRRR reform. Total general and administrative expenses were $9.0 million for the second quarter of 2025, an increase of $0.3 million or 3.5% compared to $8.7 million in the second quarter of 2024. Employee-related costs, including stock-based compensation, were $6.1 million in the second quarter of 2025, an increase of $0.7 million or 13.7% compared to $5.4 million in the second quarter of 2024. The increase in noncash stock-based compensation costs related to a onetime acceleration of approximately $1.6 million in the second quarter of 2025 due to the termination of an employee, which we do not expect to recur in the second half of 2025. This compares to unrecognized stock compensation costs of $4.9 million that will be recognized over approximately the following [ 3 and 1/4 ] years. Before turning to our operating segment metrics, I want to address the recent taxable changes occurring with the passage of the One Big Beautiful Bill Act. On July 4, 2025, this bill was signed into law. Tax changes are enacted in the period past, and as such, we will adopt applicable changes beginning in the third quarter of 2025. This legislation includes significant tax and spending policies, extends or enhances various components of the Tax Cuts and Jobs Act and made various changes to the tax credits included in the Inflation Reduction Act. Please refer to our 2025 second quarter Form 10-Q filed on August 6, 2025, for various aspects of the tax law changes we are reviewing. Included in our second quarter 2021 tax provision is approximately $0.8 million in tax benefits from investment tax credits for certain qualifying property resulting from our 2024 Pico digestion expansion project. Based on our Pico project study, we are better positioned to understand the Inflation Reduction Act investment tax credits for qualifying projects and assets. For other qualifying projects, we now believe that approximately 50% to 75% of the project capital will qualify for investment tax credits and depending upon a wide variety of factors for projects started within safe harbor guidelines, the tax benefits could range up to 30%. Related to our second Apex RNG facility placed into service this quarter, we expect to generate tax attribute benefits in our 2025 tax year and to include these benefits in our annual tax provision as of December 31, 2025. For estimation purposes, we believe that based on approximately 50% of the project capital qualified and with safe harbor guidelines not being met, investment tax credits could range between $1.0 million and $2.1 million for this project. For similar other qualifying projects, we continue to believe that 50% to 75% of the capital will qualify at a 6% to 12% investment tax credit, subject to various safe harbor applicability. Turning to our segment operating metrics. I'll begin by reviewing our Renewable Natural Gas segment. We produced 1.4 million MMBtu of RNG during the second quarter of 2025, flat as compared to $1.4 million during the second quarter of 2024. Our Rumpke facility produced 67,000 MMBtu more in the second quarter of 2025 compared to the second quarter of 2024 as a result of the previously disclosed reduction in feedstock inlet and process equipment failures, which occurred in the second quarter of 2024. Offsetting this increase was the fourth quarter 2024 sale of our Southern facility, which produced 22,000 MMBtu in the second quarter of 2024. Revenues from the Renewable Natural Gas segment during the second quarter of 2025 were $40.8 million, an increase of $2.0 million or 5.1% compared to $38.8 million during the second quarter of 2024. Average commodity pricing for natural gas for the second quarter of 2025 was 82.0% higher than the prior year period. During the second quarter of 2025, we self marketed 11.1 million RINs, representing a $1.1 million increase or 10.5% compared to 10 million RIN self marketed during the second quarter of 2024. Average pricing realized on RIN sales during the second quarter of 2025 was $2.42 as compared to $3.12 during the second quarter of 2024, a decrease of approximately 22.4%. This compares to the average D3 RIN index price for the second quarter of 2025 of $2.36 being approximately 26.1% lower than the average D3 RIN index price for the second quarter of 2024 of $3.20. At June 30, 2025, we had approximately 0.3 million MMBtu available for regeneration, 3.0 million RINs generated but unseparated and 0.1 million RINs separated and unsold. At June 30, 2024, we had approximately 0.4 million MMBtu available for RIN generation and 4.7 million RINs generated and unsold. At June 30, 2024, there were no RINs generated, but unseparated. Our operating and maintenance expenses for our RNG facilities during the second quarter of 2025 were $17.0 million, an increase of $3.1 million or 22% compared to $13.9 million during the second quarter of 2024. We do not anticipate approximately $1.8 million of nonlinear discrete expenses to occur -- to recur in the second quarter -- in the second half of 2025 as they relate primarily to annual preventative maintenance and gas processing equipment preventive maintenance. The primary drivers of the 2025 second quarter increase of $3.1 million were timing of preventative maintenance, media change- out maintenance and other wellfield operational enhancement programs at our Apex, McCarty, Rumpke and Atascocita facilities. We produced approximately 42,000 megawatt hours in renewable electricity during the second quarter of 2025, a decrease of approximately 3,000 megawatt hours or 6.7% compared to 45,000 megawatt hours during the second quarter of 2024. Approximately 2,000 of this decrease relates primarily to the planned timing of preventative engine maintenance at our Bowerman facility. Revenues from the Renewable Electricity facilities during the second quarter of 2025 were $4.3 million, a decrease of $0.2 million or 4.5% compared to $4.5 million during the second quarter of 2024. The decrease was primarily driven by the aforementioned decrease in our Bowerman facility production volumes. Our Renewable Electricity generation operating and maintenance expenses during the second quarter of 2025 were $4.8 million, an increase of $0.1 million or 2% compared to $4.7 million during the second quarter of 2025. We do not anticipate approximately $1.4 million of discrete expenses primarily associated with our Bowerman facility to occur -- to recur in the second half of 2025 as they relate to nonlinear annual preventative maintenance. The nominal resulting increase in the second quarter of 2025 was primarily driven by an increase in noncapitalizable costs at our Montauk Ag Renewables projects in Turkey, North Carolina. Offsetting the increase our Tulsa facility operating and maintenance expenses decreased approximately $0.2 million, primarily related to wellfield collection enhancements. During the second quarter of 2025, we recorded impairments of $0.4 million, an increase of $0.2 million compared to $0.2 million in the second quarter of 2024. The increase primarily relates to specifically identified assets deemed obsolete or nonoperable. We did not report any impairments related to our assessment of future cash flows. Operating loss for the second quarter of 2025 was $2.4 million, a decrease of $3.3 million compared to an operating income of $0.9 million for the second quarter of 2024. RNG operating income for the second quarter of 2025 was $9.2 million, a decrease of $2.5 million or 21.2% compared to an operating income of $11.7 million for the second quarter of 2024. Renewable Electricity generation operating loss for the second quarter of 2025 was $2.3 million, an increase of $0.3 million or 19.2% compared to the $2 million operating loss for the second quarter of 2024. Turning to our balance sheet. At June 30, 2025, $50 million was outstanding under our term loan, and we had approximately $20 million of outstanding borrowings under our revolving credit facility. As of June 30, 2025, the company's capacity available for borrowing under our revolving credit facility was $97.4 million. For the first 6 months of 2025, we generated $17.3 million of cash from operating activities, an increase of 19.3% compared to $14.5 million for the first 6 months of 2024. Based on our estimate of the present value of our Pico earn-out obligation, we reported an increase of $0.8 million to the liability at June 30, 2025. This increase was recorded through our RNG segment royalty expense. For the first 6 months of 2025, our capital expenditures were approximately $45.3 million, of which $27.7 million, $8.4 million and $7.3 million were related to our ongoing development of Montauk Ag Renewables, a contractually obligated Rumpke RNG relocation and our second Apex facility, respectively. As of June 30, 2025, we had cash and cash equivalents net of restricted cash of approximately $29.1 million. We had accounts and other receivables of approximately $7.5 million. We do not believe we have any collectibility issues within our receivables balance. Adjusted EBITDA for the second quarter of 2025 was $5.0 million, a decrease of $2.0 million or 28.6% compared to adjusted EBITDA of $7.0 million for the second quarter of 2024. As briefly noted, for the second quarter of 2025, we incurred the following discrete nonlinear expenses, approximately $1.5 million within general and administrative expenses for accelerated stock-based compensation and approximately $1.8 million and $1.4 million, respectively, within RNG and REG operating expenses relating to the timing of discrete preventative maintenance. We do not expect these discrete and non-inlayer expenses to recur in the second half of 2025. EBITDA for the second quarter of 2025 was $4.6 million, a decrease of $2.1 million or 31.3% compared to EBITDA of $6.7 million for the second quarter of 2024. Net loss of the second quarter of 2025 was $5.5 million, an increased loss of $4.8 million as compared to $0.7 million for the second quarter of 2024. Our income tax expense increased approximately $1.5 million for the second quarter of 2025 as compared to the second quarter of 2024. The difference in effective tax rates between 2025 second quarter and the 2024 second quarter primarily relate to changes in pretax loss for the second quarter of 2025 as compared to the second quarter of 2024 pretax profit. Additionally impacting our second quarter 2025 tax provision was the discrete impact of the affirmation to accelerated stock vesting and the Inflation Reduction Act investment tax credits. I'll now return the call back over to Sean.
Sean F. McClain:
Thank you, Kevin. In closing and though we don't provide guidance as to our internal expectations on the market price of environmental attributes, including the market price of D3 RINs, we are reaffirming our full year 2025 outlook provided in May 2025. For 2025, we continue to expect our RNG production volumes to range between 5.8 million and 6 million MMBtus with corresponding RNG revenues to range between $150 million and $170 million. We note that these ranges have not changed relative to our 2025 expectations as we continue to manage through regulatory uncertainty. We continue to expect our 2025 Renewable Electricity production volumes to range between 178,000 and 186,000 megawatt hours with corresponding Renewable Electricity volumes to range -- revenues to range between $17 million and $18 million, again, unchanged from our previous guidance. And with that, we will pause for any questions from our analysts.
Operator:
[Operator Instructions] Our first question comes from the line of Matthew Blair from TPH.
Matthew Robert Lovseth Blair:
And I have 2-parter here. The first is on the D3 RVO. And Sean, thanks for your comments to start thins off. But it looks like this year's D3 RIN generation is on pace not just to easily exceed the RVO for 2025, but also the proposed numbers for 2026 and 2027. Are you sharing anything that the EPA may reconsider these composed numbers and move them higher? Like is there any hope for a better RVO for the RNG space? And then the second question is you highlighted that RNG OpEx moved up in the second quarter. It sounds like that was mostly onetime preventative maintenance, media change-outs, things like that. It looks like the royalty share also moved up to about 21% in Q2 versus 19% in Q1. Would you expect that royalty share to stay around 21% for the third and fourth quarters? Or would that move down as well?
Sean F. McClain:
I will take the first part related to the RVO. As we're all aware, the RVO is still within a common period. And obviously, a data point that they are taking into consideration is that imbalance between the run rate of production and generation of D3 RINs and what the RVO proposed to be set. And so that continues to be evaluated by the EPA with that potential change pending. Kevin, perhaps you can comment on the OpEx.
Kevin Andrew Van Asdalan:
Yes. And yes, we expect to not have the approximate $1.8 million within RNG and the $1.4 million within our REG segments to recur in the second half of the year. These were planned expected preventative maintenance items that, again, occur generally once a year. So that's why we wanted to highlight the fact that we had these preventative maintenance impacts incurring now primarily in the second half of this year, and we don't expect to incur those levels of expense in the second half of this year. Specifically in regards to that royalty calculation, that was a onetime -- we address our Pico earnout quarterly as we're reporting based upon our expectations of future results of our Pico location. However, the increase this quarter was related to a discrete impact of us receiving our final tranche increase of feedstock [ Manor ] associated with the expansion of feedstock that led to our building and commissioning the CFTR increasing our digestion capacity. With us receiving that final increase and making a final payment to the dairy for that [ Manor ] increase, we reduced our discount rate, i.e., we reduced the risk of us not receiving that. So it was a sort of a formulaic calculation associated with a discount rate in our expectations as opposed to anything necessarily changing with the results or operations at Pico. So that onetimer influenced our second quarter RNG royalty expense. And on a run rate standpoint, we would expect that production revenue, notwithstanding on our tiered royalties to normalize back at that approximate 20% level.
Operator:
Our next question comes from the line of Tim Moore from Clear Street.
Tim Moore:
Just a couple of quick questions. Your operating and maintenance expense rose significantly since last October, [ it's in the ] revenues. You discussed -- which was nice to quantify the discrete $1.8 million, $1.4 million other expenses that won't really be incurred at that level in the second half. Are there any other expenses you can think of as you look at your projects, whether it's swine, anything else you're doing that might drag down some of the profitability in the second half of this year or early next year? Just kind of curious about that as we kind of look at the second half of this year and into next year.
Kevin Andrew Van Asdalan:
Thanks for the question, Tim. Generally, we see -- we do some planned outages at our facilities early in the year. Specifically some outages at our McCarty location with a planned outage that drove an increase in power controls and equipment controls and things like that. But generally, for the second half of this year, we don't expect those large onetimers to continue in the second half. If you look back at our first half of this year compared to first half of last year, you'll see that generally -- for our existing locations, we generally incur higher expenses in the first half versus lower expenses in the second half. So presuming that our timing of outages continue, I would expect that, that run rate, if you will, in the future to continue. However, occasionally, our outages are impacted if we receive word from our outbound utilities that there's going to be some outages impacting us. We might change the timing of our planned outages or if we are looking at other preventative maintenance that indicates that we need to do something else with the equipment at either an RNG or a power site, we might move that around. But a long-winded way, Tim, of saying that as of right now, as we're entering into our detailed bottoms-up budgeting for 2026, I don't necessarily anticipate any change from our historical run rate of 2025 or our second half of 2025 expectations being lower than the first half of this year nor a robust change in our timing or overall level of expenses into 2026.
Sean F. McClain:
So just a summary of things that could happen, not things that we have any anticipation of. One other comment that's probably not material, but at least worth mentioning is if you're looking at operating expenses on a percentage basis of production or revenue, there is a baseline of noncapitalizable costs associated with our build-out at Turkey. And so where you will see those costs continue, they're not currently paired with production or revenue and have a disproportionate impact as your onboarding staff and personnel and you're doing certain things to run the facility equipment that we've already commissioned down their utility charges and whatnot. Those things will continue to ramp up, but what will be significant is when we get into the early part of '26, it will be matched with your revenue and your production coming from that new facility.
Operator:
Our next question comes from the line of Betty Zhang from Scotiabank.
Y. Zhang:
I wanted to ask about the JV that you announced. Could you please elaborate on perhaps what's the nature of that JV and a big contribution by the partners? And maybe should we understand it as distribution of RNG? How should we think about that?
Sean F. McClain:
I think the best way to explain or give a little more detail behind that JV is the comments that we made regarding the positioning that the EPA has been taking. As they've been adjusting the RVO for the -- proposed RVO volumes for this year in the outward years, they've been explaining. They've been very verbal about that they have this concern that the growth and the usage of RNG into transportation is not growing at the pace of the potential production of RNG, knowing that, that's your critical path, no pun intended, for the generation of the 3 RINs, they have slowed the growth percentages that they've applied to those RVOs. And so rather than fixing volumes at lower pricing, or looking for alternative usage of the feedstock biomethane for something other than the production of RNG and the underlying RIN, we have focused on trying to form pathway opportunities that are new, unique proprietary that qualify for these transportation usages. The ability to do that, that has been acknowledged by the EPA is an opportunity to offset those perceived growth slowing of the usage of the RNG into transportation and allow for that to be more commensurate to the growth of the production of RNG should go well to offset the approach that the EPA is currently taking to try and keep those growth volumes slower, but at a minimum, opens up the opportunity short term for a large amount of volumes that the industry is claiming that do not have a home for usage in the RNG transportation space.
Kevin Andrew Van Asdalan:
And then also, Betty, to address your contribution question, we've contributed approximately $2.3 million and subject to various triggers and requirements within the underlying agreement, we can contribute potentially up to an additional $2.1 million. So our contribution in the form of capital could approximately up to $4.5 million as well as the technical understanding and know-how associated with transacting RINs. The other partners are bringing in what we would consider the IP, the relationships and these new and unique pathways to dispense third-party volumes and separate K3 from K2 RINs.
Operator:
Our next question comes from the line of Tim Moore from Clear Street.
Tim Moore:
So Sean, for the North Carolina Ag swine project, when might you get a better understanding maybe of the expansion potential there? It seems like it would just be highly incremental margin as you build that out more and the demand there ramps up. And just curious, investors are always asking me, beside that project, what else you're the most excited and enthusiastic about as you look out the next 12 to 18 months for the company?
Sean F. McClain:
That's a great question, Tim. Obviously, before we seek to do rapid expansion of that opportunity in North Carolina, it's critical to the company that we commissioned the first phase of this, and it's done so with predictable long-term fixed price offtake arrangements. The opportunity to do that and to take advantage of the enhanced legislation has really caused a very refined focus and optimization as to what it is that we intend to do in North Carolina, predominantly address the growing need for the farming community to remove this waste from their core business and to do so in a way that removes the most amount of noncaloric liquid and to have a very optimized dry pelletized product that is specifically now for the generation of just electricity and take full advantage of that legislation change that was passed at the end of the year. The expandability, you are correct. There is an economy of scale there that can be reached quite enthusiastically with the optimization of the farm side collection, the optimization of the pelletization and the continued suite of combustible fuel supply that comes out of our patented reactor process that allows for you to continue electric generation to segue into gas generation and the continuation of a valuable biochar product that is used as fertilizer and soil amendments. There's a lot of directional flexibility that happens on a project that has -- the way that we are building this. The opportunity for both the electric and the gas interconnections, the opportunity for pelletized waste, the opportunity that we have on this campus for rail transportation that could allow for us to reach beyond not only from a feedstock inlet, but also a production outlet in the form of the pelletized waste that we're creating. There's a variety of different directions that, that project can be taken for future expansion. And notwithstanding the cost reductions that you can get from further horizontal or vertical integrations particularly in the manufacturer and the securing of the raw materials that go into the production of even our reactors. The space that we have taken in Turkey, North Carolina is sufficient for a lot of these additional expansion opportunities or optimization opportunities. And we continue to work with local municipalities and government agencies to pursue any types of tax credit or incentive opportunities to expand what we believe is a very exciting project that we've taken on. I'm excited about all projects that we have in the company. It is a very fortunate position for a company that's been in this business as long as it has to have everything from its traditional landfill RNG conversion opportunities or additional electric gen opportunities to be in second and third phases of its shift to an increasing level of commodity-based revenue streams. The opportunity to take on the large-scale production of biogenic carbon dioxide in a commodity base that has the upside of potential tax credit revenue, but doesn't have the attribute risk associated with that commodity. And the ability to look at projects that may be limited in terms of size and scope or proximity to a pipeline for RNG injection and look at the opportunity to develop those with a very efficient technology in the form of methanol production are the 2 areas that I think are very nice balances to our continuation to materially and enthusiastically be in the generation of D3 RINs. So those are the items that keep us the most excited all the while we continue to evaluate for existing and future opportunities in sort of the legacy business that we have landfill gas to RNG and the subsequent generation of RINs.
John Ciroli:
And Tim, we could also point you to the press release yesterday between Montauk Renewables and Emvolon for the joint development -- joint venture between our companies that was mentioned in today's call for the 50,000 gallons per year of green methanol looking to be produced.
Operator:
Thank you, everyone. This concludes the question-and-answer session. I would now like to turn it back to Sean for closing remarks.
Sean F. McClain:
Thank you, and thank you for taking the time to join us on the conference call today. We look forward to speaking with you when we present our third quarter 2025 results.